SNo. DESCRIPTION OF WORK
CLIENT
QTY
LENGTH
01 Contract #:SSGC/SC/TE-434/Cont-490/2005 Installation of 20" Diameter x 0.438" W.T. Steel Gas Pipeline (API 5L-X60) under Canal by Horizontal Directional Drilling (HDD) at following locations:

1) Pat Feeder Canal (Completed)
2) Frontier Wah (Completed)
3) Naseer Wah (Completed)
4) Shahi Wah (Completed)
SSGC



1
1
1
1
596M Ø20"
02 Contract #:SSGC/SC/TE-600/Cont-602/2006
Installation of 16” & 20" Diameter x 0.375" & 0.438" W.T. Steel Gas Pipeline (API 5L-X60) under Canal by Horizontal Directional Drilling (HDD) at following locations:

1) Begari Canal Crossing km 70 + 781 (Completed)

2) Rohri Canal Crossing mp 77 + 2100 (Completed)

3) KP East Crossing mp 77 + 2800 (Completed)
SSGC




1

1

1

 

140M Ø20"

363M Ø16"

03 Contract #: PL/MANCH/8025/2005
Re-Routing / Byepass of Manchar Lake Segment of 16" Diameter x 0.5" Steel KMK Pipeline (API 5L-X46) at DADU
1) ARAL WAH 1 Crossing by HDD (Completed)
2) ARAL WAH 2 Crossing by HDD (Completed)
PARCO

1

1
 
04 Installation of submerged 24"dia x 0.469", 20"dia x 0.438" and 18" dia x 0.406" W.T, API5L Grade X70/ X60 high pressure Steel Gas Pipelines under canals/crossings using HDD method at the following locations (awarded)

1) Nusrat Branch (KM 136 + 188) 24" & 20" ØP/L Actual Qty 84+96=180M (completed)

2) Nara Canal (KM 39 + 57) 24" Ø P/L (Completed)

3) N.W. Canal (KM122 + 917) 20" 18"Ø P/L (Completed)

4) Begari Canal (KM 22 + 161) 18"Ø P/L (Completed)
SSGC





2

1

2

1

 


456M Ø24"

260M Ø20"

340M Ø18"

05 Purchase Order #: 508384/55/05
Fateh Shah – 1 to Makhdumpur 4" Dia (Steel Casing)
Jafara Wah Crossing by HDD in Badin Concession Area (Completed)
British Petroleum
Pakistan Inc.

1

37M
06 Purchase Order #: 508812/F5/05
Polyethylene Pipeline (4" Dia Steel Casing)
Pir Wah Crossing by HDD in Badin Concession Area (Completed)
British Petroleum
Pakistan Inc.
1 65M
07 Order Reference #: SUN CNG 168/2006
12" Ø Steel Pipeline Crossing by HDD at Mehran Highway, Landhi, Karachi for 8" Ø Gas carrier pipe (Completed)
SUN CNG Total Petrol Pump 1 65M
08 Ø 6" 0.25" W.T DN 150 Carbon Steel Pipeline (API5L Gr. B) RBOD Crossing at BHP Zamzama Phase – II Project, DADU (Completed) BHP/DESCON 1 170M
09 16" Diameter x 0.5" W.T MFM Pipeline (API5LX-46) crossing by HDD method at Upper Gogera Branch Canal, District Sheikhupura, Faisalabad (Completed) PARCO 1 120M
10 8" dia gas gathering lines between MD13 – 3 and MD 6 - 9 crossing underneath the Shah Minor Canal using Horizontal Directional Drilling (Completed) Mari Gas Co. Ltd 2 152M
11 Nirli Minor Canal crossing using Horizontal Directional Drilling for 20" dia gas pipeline for 175MW, CCPP at Daharki (Completed) Foundation Power Company Ltd 1 84 M
12 Crossing of Chandan Wah Canal at Johi Road for 8" 13% Cr. SS Duplex X-65 Gas Pipeline and Fiber Optic Cable/Conduit using Horizontal Directional Drilling System for ZAM – NORTH Pipeline Project (Completed) BHP 3 330M
13 Laying of 16" dia pipeline through HDD Method at Masu Wah Canal (Completed) FFC/Amtech 1 75M
14 Other various HDD crossings 6" to 20" Ø have been executed on different locations. Various 550M